20.11.2015 LNG tanker Al Nuaman on its way from Qatar to Poland

The first supply of liquid natural gas (LNG) to the LNG terminal in Świnoujście will be delivered by Q-Flex vessel Al Nuaman. The LNG tanker was loaded in the Qatari port of Ras Laffan on November 19th 2015 and left for Poland during the night.

The vessel is expected to reach the terminal on December 11th or 12th 2015. The first delivery of liquid natural gas, handled by Qatargas – the world’s leading LNG producer and operator of the largest fleet of LNG carriers, will be used in the commissioning and cool-down of the Świnoujście LNG terminal. The contract was signed in September 2015 by Polskie LNG and Polskie Górnictwo Naftowe i Gazownictwo SA, which serves as an intermediary for the purposes of LNG supplies to the terminal.

 